2023 Capital Improvement Project

Phase 1: Septic Replacement

April 2026 to August 2026 

In Progress

  • Complete Septic Replacement
  • Jr. – Sr. High Parking Lot Reconstruction
  • Fiber Optic Cable Replacement: between the Elementary and Jr. – Sr. High School side and front parking lots

 

Phase 2: Building Renovations

March 2025 to September 2026

In Progress

  • Basketball & Play Court – will be repaired to address pooling concerns
  • Jr. – Sr. High Front Entrance Stairs – will be reconstructed due to construction concerns

Completed

  • Auditorium Renovations
  • Elementary Library Media Center
  • Elementary Kitchen Renovation
  • Elementary Cafeteria Renovation
  • Elementary Porticos
  • Jr. – Sr. High Science/FACS Room Renovations
  • Jr. – Sr. High Main Office Renovations
  • Jr. – Sr. High Tech Suite Renovations

 

Phase 3: Elementary Gym Renovations

March 2027 to October 2028

Capital Project Update Video

May 2025

Project Passes: 158 Yes, 60 No

Graphic with text "THANK YOU VOTERS! 2023 Capital Improvement Project Passed" with checkmarks and a logo.

Tax-Neutral Renovation Project Proposed For Cato-Meridian CSD

On Tuesday, January 10, 2023, the Cato-Meridian Central School District is asking its residents to consider approving a 33.1 million dollar improvement project referendum to make capital improvements and educational enhancements to both of our schools. The District will utilize state building aid, future retirement of debt, and funds in reserve to ensure no additional taxpayer cost from this project. 

 

This proposed project is equally balanced between our Elementary and Junior-Senior High School. 

 

Highlights among the proposed items are: 

  • Replace entire septic system to address DEC violations 
    Recoat Existing Roof Systems to extend warranties 
    Kitchen and Serving Lines Reconstruction 
    Portico Columns Reconstruction 
    Reconstruction to Walkways, Curbing, Stairs, etc. 

  • Reconstruction of the Library/Media Center at Elementary School 
    Update existing Tech, STEM, and Agriculture spaces at Junior-Senior High School 
    Science and Family and Consumer Science Classroom Reconstruction 

  • Elementary (Old MS Gym) Gym Reconstruction 
    Elementary School Auditorium Upgrades 
    Upgrades to Stadium Lights 

Voting reminder with financial and distribution charts for a $33.1M school project with no tax impact.